Amber Ridge Apartments

Lead Walk Replacement

Project Overview

Concrete Jack was contracted to fix displaced steps from tree roots. Concrete Jack scrapped the tree roots and formed the steps into a ramp to make it more handicap accessible.

Project Details

Project Length: 1 day

SF of sidewalks stabilized/lifted: 48 square feet

Repair Description: 

  • Demoed and repoured sidewalks to make walkway handicap accessible 
  • Scraped tree roots under slab to minimize trip hazards and prevent further displacement. 
Before
After

Outcome

  • Created a walkway that was handicap accessible
  • Worked on other trip hazards throughout the property to concrete to create safe walkways for the residents.